Here we undertook the task of site clearance for a new client. This site required the removal of just over 800 tons of concrete flooring and slab, some reinforced with fibres and mesh.
Some of the concrete break out was put through a crusher on site to be used as a hard standing for building materials.
Once this was completed the whole site was levelled and raked over in preparation for building works to commence.
This project took just over 2 weeks to complete working within the confined hours of 9am-5pm Monday to Friday so as not to cause to much distress to local housing. All residents within the close proximity of the site were inf
rmed of the inevitable tool noise and working hours.